Many rear extensions in Essex and Suffolk are planned over, or very close to, a shared drain. Since 2011, most shared drains and lateral sewers serving more than one property have been public sewers owned by the water company, even when they run through private gardens. Building over or near one needs the water company's consent.
This guide explains when an agreement is needed, how the process usually runs and how it affects the foundation design and programme. Requirements vary by water company and change from time to time, so always check the current guidance for your property.
When you need one
A build over agreement is generally needed when an extension, conservatory or other structure is built over a public sewer, or within three metres of one. Across most of this area the sewerage undertaker is Anglian Water, which publishes its own criteria and application process. Building Regulations also require building control to consult the water company where work is near a public sewer.
Start by checking the sewer records for your property and lifting any inspection covers in the garden. A drain that serves your house alone is usually private. One that also carries a neighbour's waste is likely to be public.
How the process usually runs
The water company will want drawings showing the extension, the sewer, its depth and any manholes. Many require a CCTV survey of the pipe before work starts, and some ask for another after completion to show it was not damaged. Simpler cases may qualify for a quicker self-certification route. Allow several weeks for an agreement to be issued, and apply early so the start date is not held up.
- Check sewer maps and inspection chambers
- Commission a CCTV survey if required
- Prepare drawings showing the pipe and foundations
- Apply to the water company with the fee
- Keep the agreement with the property records
What it means for the foundations
Foundations near a sewer must not load the pipe or leave it unable to be maintained. That can mean taking foundations deeper than the pipe invert, bridging over it with a lintel or reinforced beam, or using a different foundation type designed by an engineer. A manhole inside the footprint may need to be moved or replaced with a sealed access fitting, which usually requires specific approval. Our extension foundations cost guide explains how depth and design change the price.
Costs to allow for
Water company application fees are published on their websites and change over time. A CCTV drain survey from a specialist commonly costs a few hundred pounds. Diverting a sewer to avoid the footprint altogether is a larger job, often running into thousands of pounds, and needs its own approval. These sums are broad guides, not our prices. Your actual figure follows a review of your drawings and plot.
Finding out what is under the garden
Sewer records held by the water company show the public network, but they are not always complete or exact for older shared drains. Lift every inspection cover between your house and the boundary and note which way the pipes run, how deep they are and whether flow from next door joins your run. A dye test, or a short CCTV survey, removes the guesswork.
Older terraces and semi-detached houses commonly share a single run along the backs of several gardens. Detached houses more often have their own private drain until it meets the public sewer near the boundary or under the road.
Building it into the extension programme
Treat the agreement as a dependency in the same way as planning and building regulations approval. Apply once the drawings and foundation design are settled, and do not let the groundworks start until the water company has responded. If a manhole inside the footprint must be moved, the new chamber and pipework are usually built before the main foundations are dug, which adds a short stage at the front of the programme.
Selling the house later
A buyer's solicitor will usually ask whether an extension was built over or near a public sewer and, if so, for a copy of the agreement or completion paperwork. Without it a sale can stall while retrospective consent is sought, which can involve another camera survey and sometimes opening up the ground. Keeping the agreement, the before and after surveys and the building control completion certificate together with your deeds saves that delay.