A productive first day on a self-build is the result of decisions made weeks earlier. The plot should have a lawful start, an engineer-designed foundation, an agreed datum, service routes and inspection responsibilities. Otherwise plant arrives while drawings and approvals are still being interpreted.
This checklist is a coordination guide rather than legal or engineering advice. Requirements differ by planning authority, building-control body and structural-warranty provider, so each project needs its own written pre-start schedule.
Give tendering contractors the same drawing revision and written scope. Ask each to state exclusions, assumed quantities, inspection responsibilities and the defined handover point. This makes comparison far more reliable than a single total.
Finally, confirm insurance, payment stages, change control and the procedure for unexpected ground. A written route for decisions protects both client and contractor when evidence changes after excavation.
Planning permission and conditions
Confirm that permission is current and that every condition requiring approval before commencement has been discharged. Conditions may cover materials, drainage, ecology, trees, archaeology, contamination, highways or construction management.
A drawing stamped approved does not by itself prove all pre-start conditions are closed. Keep the decision notice and discharge confirmations with the working information.
Building control and structural warranty
Appoint building control or the relevant approved route and notify the intended start in accordance with its process. Agree the inspection stages, notice periods and who books each visit.
A structural-warranty provider can have separate technical standards, information requirements and inspections. Appointment after foundations are poured can limit options, so the warranty route is established before work.
CIL self-build exemption
Where Community Infrastructure Levy applies, the correct exemption claim and commencement process must be followed. A Commencement Notice must be received before development starts. Consequences for a missed deadline vary with the date and notices, so obtain project-specific confirmation rather than relying on a summary.
The exemption also has evidence and occupancy requirements after completion. Keep the approval, forms and supporting documents together, and take advice from the collecting authority before any material operation begins.
Investigation and foundation design
The engineer needs appropriate site information: soil strata and testing, tree survey, existing foundations where relevant, proposed loads and any contamination or groundwater findings. The output should state foundation type, dimensions, reinforcement and heave measures.
For clay sites near trees, the structural and warranty requirements must align. If excavation exposes different conditions, pause that element and refer it before pouring.
Drainage and service connections
Agree foul and surface-water destinations, gradients, chamber positions and any soakaway testing. Confirm points of connection and approvals where third-party sewers or watercourses are involved.
Electricity, water, data and any gas routes need quotations, lead times and entry positions. Ducts and sleeves are far easier to install before the floor is completed than after it.
Setting out, datum and logistics
A competent setting-out process transfers the approved building position and a stable datum onto the site. Boundaries should be understood and offsets checked before trenches are excavated.
Plan plant access, spoil storage, lorry turning, wheel cleaning, temporary power, water, welfare and material storage. Record adjoining surfaces and agree how neighbours and the highway will be protected.
A practical pre-start pack
- Approved architectural and structural drawings
- Discharged pre-commencement conditions
- Building control and warranty contacts
- Site investigation, tree and drainage information
- Service drawings, quotations and entry points
- CIL and commencement confirmations where applicable
- Setting-out coordinates, datum and boundary information
- Written scope, programme and inspection schedule