How to compare groundworks quotes for a larger project

Written by Matt Nash, Breaking Ground Ltd

Last updated:

Reading groundworks tenders side by side, so the cheapest-looking price does not become the most expensive build.

On a new build, self-build or large extension, groundworks quotes can differ by tens of thousands of pounds for what looks like the same job. Most of the gap is rarely profit. It is usually differences in what has been included, what has been left as a provisional sum and what has been assumed about the ground.

This guide explains how to put quotes on a level footing before choosing. It is general advice for homeowners and self-builders, and applies whoever you appoint.

Price the same drawings

Every contractor should price the same set of documents: the approved drawings, the engineer's foundation design, the drainage layout and any site investigation. If one quote assumes standard trench fill and another allows for the engineer's deeper design, they are not comparable. Send the same pack to everyone and ask each to list the drawing numbers priced.

Provisional sums and exclusions

A provisional sum is an allowance for work that cannot yet be measured, such as extra foundation depth or ground water pumping. It is not a fixed price. A quote with large provisional sums can look cheaper while carrying more risk. Compare the fixed elements first, then the allowances separately.

Read the exclusions just as carefully. Common ones include:

  • Contaminated or hazardous spoil disposal
  • Dewatering and pumping
  • Foundations deeper than the stated depth
  • Utility connection charges
  • Removal of obstructions found below ground
  • Building control and water company fees

Muck away and spoil classification

Spoil disposal is one of the largest and least visible items. Clean natural soil costs less to dispose of than mixed or contaminated material, which may need testing before a tip will accept it. Check whether each quote states the number of loads, the assumed classification and what happens if testing shows otherwise. Our muck away and grab hire cost guide covers how removal is priced.

Programme, payments and protection

Ask for a written programme that shows the start date, inspection points and when the slab or floor will be ready for the next trade. Payment should follow completed stages rather than large sums in advance. Check insurance, who is responsible for setting out and how variations are agreed and priced before the work is done.

Finally, keep a contingency of around ten to fifteen per cent of the groundworks figure until the foundations are poured and the drainage is in. That is the point at which most of the ground risk has been resolved.

Setting out, levels and who owns the risk

Every quote should say who sets the building out on the plot and who checks it against the drawings. A footprint a few hundred millimetres in the wrong place can breach a planning condition or a boundary. Ask the same about finished floor levels, because the slab height decides thresholds, drainage falls and how much spoil leaves site.

Look also at temporary works: fencing, welfare facilities, trench support and site security. They rarely appear as large figures, but leaving them out entirely usually means they reappear as variations.

A simple comparison sheet

Before choosing, set the quotes out in columns under the same headings. A one-page sheet makes gaps obvious:

  • Fixed price for measured work
  • Total of provisional sums
  • Listed exclusions
  • Assumed spoil volumes and type
  • Programme length and start date
  • Payment stages and retention

Red flags in a groundworks price

Some warning signs are worth knowing. A single lump sum with no breakdown makes later variations impossible to check. A quote that ignores the engineer's design and prices a generic foundation will almost certainly grow. Large deposits before any work starts, no written programme and vague answers about spoil disposal or insurance all suggest the price has not been thought through. None of these prove a contractor is poor, but each is a fair reason to ask more questions.

Need it sorted? Book Request a fixed groundworks quote

Services this relates to

Want the figure for your own property? Call 07770 880587 or email enquiries@breakinggroundltd.co.uk and we will arrange a site visit.

Request a consultation

We take on new build contracts and substantial driveway and garden projects. Give us the detail and Matt will come back to you personally.

By sending this form you agree to our privacy policy.

Prefer to talk? Call 07770 880587 or email enquiries@breakinggroundltd.co.uk.

Questions we are asked

Frequently asked questions

Should I always take the lowest quote?+

Not without checking what each includes. Compare fixed items, provisional sums and exclusions separately before deciding.

Is a fixed price better than a measured contract?+

A fixed price gives more certainty on known work. On uncertain ground, a fixed price with clearly stated allowances is often the fairest arrangement for both sides.

How do you price groundworks?+

From the drawings and a look at the plot, set out line by line with any allowances kept separate.

What extra paperwork should I ask for?+

Insurance details, a written programme, the drawing list priced and how variations will be agreed.

Breaking Ground. Building Trust.

Comparing tenders?

Send your drawings and engineer's design for a fixed, itemised price. We will visit, survey and quote properly.

Ten year guarantee on extensions and new builds / 30 miles of Colchester / Substantial projects